GAP.
Log in Book a demo
Project & capital business Switch to transactional

Two gaps:
one to win the work,
one to deliver it.

Winning the work is only half of budget. The revenue gap tells you whether you will hit the revenue number; the backlog gap tells you whether you can.

FOCUSING FURTHER AHEAD

Each bar is a project delivering revenue over its life. Today's revenue was sold months ago — and the right-hand side of the year is not yours yet.

ALREADY WON STILL TO BE WON Today −3 mo +9 mo
Secured — delivering now Not yet sold — the backlog gap
So what is backlog?

How much of next year’s revenue is already signed?

Backlog is signed work you have not delivered — next year's revenue, already won. Watching this forces BD to work far enough ahead of the revenue target so there are no surprises. 

01

Revenue is delivered, not sold

A project won this month recognises revenue across the months it takes to deliver. Nothing you sell today lands in full today.

02

So next year is already partly decided

The longer the average project, the more of the coming year's revenue has to already be signed. Selling harder in month ten cannot fix month eleven.

03

The cover you need is a number

Secured work equal to the average project length is the minimum book. Below that line you are relying on deals nobody has won yet.

INTRODUCING A BACKLOG TARGET

One number and two teams pulling in opposite directions = a sales machine.

Fills the tank

BD and client relations

Wins signed work into backlog. Measured on the backlog gap: how much more secured work is needed to keep delivery fed.

Award value and award date Pipeline velocity Scenario planning
WORK WON IN Backlog target BACKLOG GAP SECURED BACKLOG signed work not yet delivered REVENUE RECOGNISED OUT short of the rate budget needs = revenue gap
Empties the tank

Project management and delivery

Turns backlog into recognised revenue. Measured on the revenue gap: how much more has to be delivered this month to hit budget.

Programme dates and resourcing Percentage complete and claims Profit and cash
MEASURING THE GAPS

Once the target is set, two gaps are worth measuring.

One asks whether you can hit next year. The other asks whether you will hit this month. They belong to different halves of the business.

01

The backlog GAP

Business development and sales, long term
Opening backlog+Work wonWork delivered=Closing backlog, vs target

Backlog is next year’s revenue, so it carries a target of its own. Rolled forward every month, you see the book running thin long before it shows up in revenue.

Nothing operational closes this gap. It is closed only by selling.

02

The revenue GAP

Operations and project management, short term
Actual sales+Secured+Weighted pipeline=Revenue this month, vs budget

What the month will actually recognise: work already invoiced, plus secured work being delivered, plus weighted pipeline. What budget it leaves uncovered is the gap.

As the months run out, more of the number rests on pipeline nobody has won yet.

Worked example

One book, three wins, twelve months.

i

A worked example. Average projects here run about nine months, so the book must always hold roughly nine months of delivery — the dashed target. The existing book only ever burns down; three future wins land at months 2, 4 and 7, and none of them delivers evenly. Follow the same colours across both views.

The book of secured work
what you hold, month by month
6 12 18 24Backlog target — 9 months of deliveryBook runs thinNow+2 mo+4 mo+6 mo+8 mo+10 mo

Each win lifts the book the day it is signed, then delivery pulls it back down. Between wins the book only falls — and late in the year it drops through the target: the point where winning work stops being optional.

Revenue from the same scenario
what those projects actually bill
1 2 3 4Monthly budgetNow+2 mo+4 mo+6 mo+8 mo+10 mo

The same three wins, delivering unevenly — a strong month here, a thin one there. While the book is deep, the stack clears the budget line; as it thins, monthly revenue sags below budget. The backlog view predicts it; the revenue view is where it lands.

Existing book Win 1 — month 2 Win 2 — month 4 Win 3 — month 7 · delivers into next year Backlog target Monthly budget
Who watches it

The key roles that need this number.

CEO / managing director

Which deals must we win, and have we got the resource to land and deliver them?

Decision: deals we chase or decline, and how we price and resource them
BD manager

A named mandate, not a vague target: these awards, at this value, by this date —to close this gap. 

Decision: where the team spends bid effort this month
Operations / delivery lead

Have we got the capacity to deliver the revenue, where can we push or pull to utilise capacity?

Decision: hire, redeploy, subcontract, or hold - gross profit management
CFO

The early warning sign of revenue coming down or the que to build and maximise profits.  

Decision: cost action, covenant and cash headroom, guidance, board reporting
The software

See the GAP on real numbers.

The actual forecast: backlog, pipeline and the gap to budget, laid out the way you'd work it. Switch between divisions, and click any CRM line to see the deals behind it.

GAP · Apr 26 – Mar 27
+499,438
Weighted forecast
39,621,438
Budget
39,122,000
Key deals this month 4 deals · $1.8M full value
Northgate Stage 2
A. Reid · proposal, decision this month
$840k
Tauranga Depot fit-out
M. Iona · tender submitted
$465k
Hillside civil works
A. Reid · negotiation
$310k
Eastgate maintenance
J. Park · annual renewal
$188k
The deals this month's forecast leans on.
Chase list Gap to close $814k
Northgate Stage 2
A. Reid · closes the April gap on its own
$840k
Hillside civil works
A. Reid · biggest slipped deal in the month
$310k
Tauranga Depot fit-out
M. Iona · decision due this week
$465k
Eastgate maintenance
J. Park · renewal, low effort
$188k
Ranked by impact on the gap, not deal size.
Accumulated revenue vs budget
$
Apr 26Jun 26Aug 26Oct 26Dec 26Feb 27Mar 27
Actual+ Secured+ PipelineBudget

Real Meridian figures, shown the way you'd work them. The formulas that build the forecast run in the background, which is the part doing the work and the part you don't see here.

Get started

See your GAP in one session.

Bring a CSV of your pipeline and budget, and we'll show you the gap on your own numbers.

Book a demo
Next: scenario planning

Seen the GAP? Now plan the deals that close it.

Your team calls every open deal green, yellow or red, and each call rebuilds the GAP — a certain, an optimistic and an ambitious distance to budget, from one board.*

Scenario planning →
* Included in specific GAP plans rather than every plan — we walk through which plan covers what in the demo.